Thread: Completion time for Custom Home

  1. #1
    Join Date
    Dec 2010
    Location
    God's Country
    Posts
    1,788

    Default Completion time for Custom Home

    What is the average length of time in today’s market one should expect a 2800sq ft home to be completed, start to finish? Our contractor told us 8-12 months when we signed the contract and should’ve had a deadline in the contract but we really didn’t think about it at the time. We are about to hit month 13 of actual work and there was a month before that where nothing was done. There was a month from the day I gave him 10% cash to start until the footings were dug. Signed the contract in March of 2021. It’s like we can’t get a full weeks work out of them to get this thing finished and it’s one excuse after another why the subs aren’t showing up. I’m about to come unglued about it, honestly. But what good would it do?

  2. #2
    Join Date
    Mar 2004
    Location
    Columbia
    Posts
    9,141

    Default

    We just started one at the farm. Not quite that big. Hell, it took us almost 3 months to get Clarendon County to give us a permit. We have already run into shortages of brick and mortar. I’m glad it isn’t my primary residence.
    Them that don't know him won't like him, and them that do sometimes won't know how to take him

    He ain't wrong, he's just different, and his pride won't let him do things to make you think he's right

    They don't put Championship rings on smooth hands

  3. #3
    Join Date
    Nov 2005
    Location
    Here, There, Everywhere
    Posts
    5,054

    Default

    is this the same gc you started a thread about last year that was doing such shitty work?

    yes you should've put in a completion date into the contract before signing, but you already know that. supply chain is still fucked so all building material is hard to get right now and any subcontractors worth their salt are still booked months out from now.

    not sure what your payment terms are, but withholding money is your only option to get gc to complete.
    "JUST BECAUSE I AM NOT A GOOD SPELLER DOESN'T MEAN MY JEAN POLL IS GONNA BE BAD."
    Quote Originally Posted by Mergie Master View Post
    There's evidence coming out...
    Quote Originally Posted by Cottontop74 View Post
    I dabble in a lot of things, but don't get too technical with any of them.

  4. #4
    Join Date
    Oct 2007
    Location
    Blythewood
    Posts
    16,973

    Default

    Don't come unglued. You're in the short rows now.

    There's no excuse to take a year. None.
    "Freedom Isn't Free"
    _Spc. Thomas Caughman
    1983-2004

    Quote Originally Posted by Dook View Post
    Go tigers!

  5. #5
    Join Date
    Feb 2009
    Location
    Chapin
    Posts
    6,787

    Default

    I purchased another house a year ago with a rent back agreement to the old owners, letting them rent until their new build in dunes west was done.

    The target date for the completion was mid January. They are still renting from us today and have 2 more weeks before they can get the CO from mount pleasant.
    Quote Originally Posted by Rebel Yell View Post
    now Hogan can fuck off on here all day and call it work, thanks!

  6. #6
    Join Date
    Jan 2010
    Location
    Greenville, SC
    Posts
    4,989

    Default

    We just finished one. 18 months from the day the grader showed up.
    I was stressed like you about the 12 month mark.
    What I experienced was that anything standard.....like a standard window or garage door, was not bad to get. Once you start custom work the wait times went up exponentially. 30 weeks for a custom color garage door. 25 weeks for a custom window. The custom engineered beams my neighbor bought took over a month. We had a stone shortage, then we had to wait on the masons. Don't even get me started on appliances.
    Same guy built plenty of homes in 12 months in the past. This one was 18 months.
    Last edited by DJP; 05-23-2022 at 09:24 AM.

  7. #7
    Join Date
    Jan 2007
    Location
    Simpsonville
    Posts
    3,475

    Default

    Honestly I'm thinking a barndominium might be the way to go.

  8. #8
    Join Date
    Dec 2010
    Location
    God's Country
    Posts
    1,788

    Default

    Quote Originally Posted by ziggy View Post
    is this the same gc you started a thread about last year that was doing such shitty work?

    yes you should've put in a completion date into the contract before signing, but you already know that. supply chain is still fucked so all building material is hard to get right now and any subcontractors worth their salt are still booked months out from now.

    not sure what your payment terms are, but withholding money is your only option to get gc to complete.

    Yes, we had a come to Jesus meeting during the framing and all the issues were handled and we continued on. We have been pretty please with how it has gone since then other than it taking so long. The house looks great and we have been able to work with him and get some things we didn’t plan on the beginning that he is covering the cost of. But I don’t like being told we will be done in 2 weeks and nothing happens in those 2 weeks except for a few small things. This is a small contractor and currently has 5 houses going. One of his other customers started subbing his stuff out himself in January because he saw how mine was going.

  9. #9
    Join Date
    Feb 2013
    Posts
    3,542

    Default

    Quote Originally Posted by BCR3 View Post
    Honestly I'm thinking a barndominium might be the way to go.
    That’s the way I want to go but haven’t been down the financing road yet. I have heard financing can be hard to get. If anyone can shed some light, I would appreciate a pm. Don’t want to mess up the man’s thread.
    Last edited by banded_mallard; 05-23-2022 at 10:31 AM.

  10. #10
    Join Date
    Apr 2010
    Location
    Crystal Lake
    Posts
    3,646

    Default

    What are you down to? Hardware? Trim out electrical and plumbing?

  11. #11
    Join Date
    Oct 2015
    Posts
    2,265

    Default

    A good contractor should still be able to build a custom house in 6-8 months. The only reason it should go longer is if the house is truly higher end custom work that has a lot of speciality products. Sounds like your guy is a small time builder who doesn't have the resources to get it done in this market.

  12. #12
    Join Date
    Apr 2010
    Location
    Crystal Lake
    Posts
    3,646

    Default

    Quote Originally Posted by Remy View Post
    A good contractor should still be able to build a custom house in 6-8 months. The only reason it should go longer is if the house is truly higher end custom work that has a lot of speciality products. Sounds like your guy is a small time builder who doesn't have the resources to get it done in this market.
    You can barely get windows in 6 months.

  13. #13
    Join Date
    Oct 2015
    Posts
    2,265

    Default

    Quote Originally Posted by charlie horse View Post
    You can barely get windows in 6 months.
    Depends on the windows. Standard vinyl windows can be had in 2-4 months right now. I ordered mine in March and just got them in.

  14. #14
    Join Date
    Sep 2009
    Location
    Banks of the Wateree
    Posts
    41,927

    Default

    I think it was around 18 months on mine, from the okay let's start.. but I had to build a road in, clear and grade and junk. There's a house next to my lake house that's waited like Charlie has said six or seven months for windows.

    Charlie, I saw on the internets you're remodeling B's house. Tell stinkcrack I said what's up.

  15. #15
    Join Date
    Mar 2009
    Location
    Ruffin
    Posts
    1,035

    Default

    We signed a contract back around Thanksgiving..... in January we were about two weeks away from signing the construction loan when the price went up another 40k per my contractor...... so we bit the bullet and backed out. Still waiting and still renting. Good luck to all that are currently building in these times SUCK......

  16. #16
    Join Date
    Dec 2010
    Location
    God's Country
    Posts
    1,788

    Default

    Quote Originally Posted by charlie horse View Post
    What are you down to? Hardware? Trim out electrical and plumbing?
    We are at about 75% on the electrical fixtures being installed and working, interior needs final coat of paint on everything, all door hardware, back porch railing, crawl space encapsulation and dehumidifier needs installing, attic fan still needs installing, shoe mold around island and cabinets in laundry room, crawl space swell needs to be built by brick masons, 24 cedar columns on the exterior need to be stained/sealed along with front door, 3 drawers in kitchen have the wrong fronts installed on them and he prob hasn’t even ordered the right ones, master shower glass was to be installed last week and is still MIA. A few more small things. I feel like it’s a solid weeks worth of work but nobody showed up Friday to do anything and nobody is there again today.

  17. #17
    Join Date
    Jan 2003
    Location
    SC
    Posts
    24,411

    Default

    18 Mo's for a custom home that size.

    Sent from my moto z4 using Tapatalk
    Last edited by Catdaddy; 05-23-2022 at 11:08 AM.

  18. #18
    Join Date
    Nov 2014
    Posts
    13,499

    Default

    I started mine in February of 2019. Moved in in October 2020. Sounds like a bunch of white boys, not showing up on fridays and Monday's.
    "They are who we thought they were"

    You can dress a fat chick up, but you cant fix stupid

  19. #19
    Join Date
    Nov 2001
    Location
    Columbia, SC
    Posts
    47,887

    Default

    racist
    Ugh. Stupid people piss me off.

  20. #20
    Join Date
    Nov 2013
    Posts
    4,992

    Default

    I'm 19 months into an easy 24 month build on one I'm consulting on right now...

    We might need to clarify the definition of "custom" though. There is a significant amount of real estate between "not tract" and "custom". What most people love to call custom is nothing more than someone's stock plan with some nice finishes.

    I sold my place last year with intentions of doing another custom build on some property and just tabled that idea given the two plus year build time....don't have enough patience for that right now. Windows 6-7 months out...trusses and floor systems are none existent. Quality labor is booked out so far right now they can't even tell you when to expect then.

    ETA: To answer the OPs question, semi custom 10-18 months, True custom, 24-30 given the current landscape of the industry
    Last edited by FishSticker; 05-23-2022 at 12:12 PM.